SCRUM COMPLEMENTING LAST PLANNER SYSTEM – A CASE STUDY

Research output: Contribution to conferencePaperpeer-review

5 Citations (Scopus)

Abstract

Scrum emerged from the software sector and has been identified as a novel methodology that is radically different from traditional project management teaching. However, there is a paucity of data from real life case studies that affirm Scrum can benefit construction execution. This paper reports on a 20-week Scrum implementation across seven teams on a construction project that must achieve a critical building weathertight milestone. The study adopted a mixed-methods approach utilising case study design and data collected from a literature review, project documentation review, direct observation, purposeful semi-structured interviews, and a focus group workshop. Scrum complements Last Planner® System (LPS) implementations and brings specific benefits at point of work execution by reducing weekly missed tasks resulting in increased and more reliable Planned Percent Complete (PPC). An 11 percent increase in average PPC accrued from utilising Scrum to complement LPS by reducing reasons for non-completion (RNC) of work tasks at crew level work interfaces. Additional softer benefits in the form of enhanced inter-trade communications and collaboration, as well as greater involvement of the entire crew in striving to achieve task execution. Further in-practice and academic research is required in aligning construction processes and methodologies with the concepts and definitions found in Scrum.

Original languageEnglish
Pages175-186
Number of pages12
DOIs
Publication statusPublished - 2022
Event30th Annual Conference of the International Group for Lean Construction, IGLC 2022 - Edmonton, Canada
Duration: 25 Jul 202231 Jul 2022

Conference

Conference30th Annual Conference of the International Group for Lean Construction, IGLC 2022
Country/TerritoryCanada
CityEdmonton
Period25/07/202231/07/2022

Keywords

  • agile
  • collaboration
  • last planner system
  • Lean construction
  • scrum